Caselaw

Civil Appeal (Be’er Sheva) 61840-06-26 Magyad Al-Ramili v. Ismail Al-Ramili

November 18, 2026
Print
Be’er Sheva District Court
Civil Appeal 61840-06-26 Alramili et al.  v. Alramili

External bag:

 

 

Before Honorable Judge Yaakov Presky

 

 

Appealers

 

1.  Magyad Al-Ramili

2.  Mazal Alramili

3.  Omar Alramili

4.  Alramuli Spa

 

Against

 

Respondents Ismail Al-Ramili

 

Copy of a decision from a court protocol given on November 18,2026,8 Kislev 5787

 

Judgment

  1. Before us is an appeal against the judgment of the Be'er Sheva Magistrate's Court (Hon. Judge Racheli Tiktin Adullam), dated 23.4.2026, in which it was determined that between Respondent 1 (hereinafter: "Ismail") and Respondents 2-3 there was a trust transaction regarding the "small plot, " as defined below, and that Respondents 2-3 should assist Ismail in registering the small plot in his name.  In summary, it should be said that the dispute before the lower court concerned a dispute between family members regarding their rights in the plot in the settlement of Rahat.  All parties are family members.

    2.  On 5.1.2015, a development contract was signed between the Israel Land Authority (hereinafter: "ILA") and Respondent 2 (hereinafter: "Majad") and Appellant 1 (hereinafter: "Omer"), regarding rights in plot number 909 in Complex 4 in Rahat, known as Block 100840, Parcel 63, with an area of approximately1,246 approximately square meters (hereinafter: "the large plot").  According to the contract, the rights in the plot were granted to the parties in equal shares.  Just one day later, on January 6,2015, another development contract was signed between the ILA and respondents 2-3, the couple Majad and Mazal Al-Ramili, regarding rights in plot number 257 in Complex 4 in Rahat, known as Block 100840, Parcel 25, with an area of approximately 501 square meters (hereinafter: "the small plot").

    3.  According to Ismail, respondents 2-3 offered him to purchase the small plot in trust through them as "formal winners, " since they wished to purchase the rights in the large plot but did not have sufficient financial means to purchase both plots together.  According to Ismail, he acted on the plot as an owner over the years, handled the extension of the development contract with the ILA, and submitted building permit plans through an engineer starting in 2019.  We will preface by noting that from a public employee certificate submitted by the ILA during the management of the claim, it emerged that the total payments for the small plot amounted to 104,816 ₪, and that Ismail proved that he paid at least directly 14,442 ₪, and Majad even admitted in his interrogation that Ismail actually paid the remaining payment vouchers.  According to Respondent 1 in the lower court, the value of the plot is about 1.3 million ILS.